Free LEED® Green Associate™ practice test

20 questions, each with a clear explanation.

Quick PracticeQuestion 1 of 20
Your progress through this set
LEED ProcessStep 1 · Choose one answer

A team finishes documenting a LEED v5 BD+C project and submits its certification application. A new team member assumes the U.S. Green Building Council will review it. Which organization conducts the technical review?

Question review

All 20 LEED Green Associate questions with explanations

Try the set above first, then use this list to review. Each answer and explanation stays closed until you open it.

  1. Question 1 · LEED Process

    A team finishes documenting a LEED v5 BD+C project and submits its certification application. A new team member assumes the U.S. Green Building Council will review it. Which organization conducts the technical review?

    1. The U.S. Green Building Council, the group that develops the LEED rating systems
    2. Green Business Certification Inc. (GBCI), which administers certification
    3. The local building department, which issues the certificate of occupancy
    4. The commissioning provider, who verifies the building systems on site
    Show answer and explanation for question 1

    Correct answer: B · Green Business Certification Inc. (GBCI), which administers certification

    USGBC's Guide to LEED Certification lists the steps as registering, applying, receiving a technical review by Green Business Certification Inc. (GBCI), and achieving certification. The Foundations of LEED document explains that GBCI was established in 2008 as a separately incorporated entity that administers green building certification and credentialing, while LEED itself is developed by USGBC's member-based committees. So the organization that writes the rating system is not the one that reviews projects. The building department issues occupancy approvals under local codes, not LEED decisions. A commissioning provider verifies building systems, which is one prerequisite inside the application, not a review of the whole application.

    Look for this next time: USGBC develops LEED; GBCI, a separate organization, reviews project applications and administers certification and the LEED credentials.

  2. Question 2 · LEED Process

    A developer is building a new office tower. At certification, about 70% of the gross floor area will be tenant floors with no finishes and no tenant mechanical, electrical, or plumbing fit-out. Which LEED v5 rating system fits the project?

    1. BD+C: New Construction and Major Renovations, because the building is new
    2. ID+C: Commercial Interiors, because tenants will fit out their own floors
    3. O+M: Existing Buildings, because occupancy will begin floor by floor
    4. BD+C: Core and Shell Development, since most of the floors are incomplete
    Show answer and explanation for question 2

    Correct answer: D · BD+C: Core and Shell Development, since most of the floors are incomplete

    USGBC's rating system selection guidance applies LEED v5 BD+C: Core and Shell Development to new or majorly renovated whole buildings where at least 40% of the gross floor area is incomplete, meaning it lacks basic finishes or the systems needed to occupy it. Seventy percent unfinished clearly qualifies. New Construction and Major Renovations expects at least 60% of the floor area to be complete, which this tower will not be. Commercial Interiors covers interior fit-outs with no shell or site scope, which suits the tenants' later projects, not the developer's building. Existing Buildings is for whole buildings that have been fully operational and occupied for at least one year.

    Look for this next time: In LEED v5, a new building with at least 40% of its gross floor area incomplete at certification uses BD+C: Core and Shell Development.

  3. Question 3 · LEED Process

    During design of a LEED v5 BD+C: New Construction project, the owner proposes dropping fundamental commissioning because it earns no points and the team expects 64 points from credits anyway. What should the LEED coordinator explain?

    1. It is a prerequisite, so the project cannot be certified without it
    2. It can be dropped, because 64 points already reaches the Gold level
    3. It can be traded for one extra credit that is worth the same points
    4. It is only required when a project is aiming for Platinum certification
    Show answer and explanation for question 3

    Correct answer: A · It is a prerequisite, so the project cannot be certified without it

    USGBC's LEED v5 credit library lists Fundamental Commissioning as a required prerequisite for BD+C: New Construction, and the Foundations of LEED document defines prerequisites as required elements that must all be met before a project can be considered for certification. Prerequisites earn no points, so a project's total does not matter until every one is met. Sixty-four points falls in the Gold range of 60 to 79 in USGBC's certification guide, but only once the prerequisites are in place. Credit points cannot stand in for a missing prerequisite. Platinum carries additional v5 requirements, yet fundamental commissioning applies at every level.

    Look for this next time: Prerequisites earn no points but are mandatory; a point total only leads to certification once every prerequisite is met.

  4. Question 4 · LEED Process

    One project team receives a credit interpretation ruling (CIR) from GBCI that accepts its approach to a credit. A second team, working on a different LEED project, wants to rely on the same ruling. What applies?

    1. The ruling applies to every project registered after the date it was issued
    2. The second team can cite it if both projects use the same rating system
    3. The ruling covers only the project that submitted it and sets no precedent
    4. The ruling binds other projects once USGBC publishes it on its website
    Show answer and explanation for question 4

    Correct answer: C · The ruling covers only the project that submitted it and sets no precedent

    USGBC's Guide to LEED Certification says CIRs are not precedent setting: a team can use a ruling only for the project under which it was submitted. Precedent comes from LEED Interpretations, which USGBC develops with its LEED committees and publishes as addenda that apply to projects registered in the future. So the option about every later project describes a LEED Interpretation, not a CIR. Sharing a rating system does not let the second team borrow another project's ruling, and publication does not turn a CIR into a precedent. The second team can submit its own CIR or follow a published LEED Interpretation that covers the question.

    Look for this next time: A CIR guides one project only; LEED Interpretations, published as addenda, set precedent for projects registered later.

  5. Question 5 · Integrative Process Planning and Assessments

    A LEED v5 BD+C project team plans its first sustainability workshop for after the construction documents are finished, with only the architect and the LEED consultant attending. Which change best fits v5's Integrative Design Process credit?

    1. Hold a predesign charrette with the owner and at least four key perspectives
    2. Keep the workshop after construction documents, when every system is settled
    3. Leave goal setting to GBCI, which assigns project goals at registration
    4. Replace the workshop with a cost estimate prepared by the contractor alone
    Show answer and explanation for question 5

    Correct answer: A · Hold a predesign charrette with the owner and at least four key perspectives

    USGBC's Integrative Design Process credit for LEED v5 starts in predesign. It asks for a design charrette during predesign or early in design with the owner or owner's representative and participants from at least four key perspectives, such as the architect, contractor, energy modeler, and community engagement representatives. The team then sets specific, measurable goals for the three LEED v5 impact areas and builds them into the owner's project requirements. A workshop after construction documents comes too late to change how systems interact. GBCI reviews applications; it does not set a project's goals. A contractor's estimate is useful input, but one discipline working alone is the opposite of an integrative process.

    Look for this next time: The v5 integrative process starts in predesign, with a multidisciplinary charrette and measurable goals for the three impact areas.

  6. Question 6 · Location and Transportation

    A county is choosing a site for a new library and wants to earn the LEED v5 BD+C Sensitive Land Protection credit. Which site fits that credit?

    1. An undeveloped lot where the building footprint would sit 40 feet from a wetland
    2. A field of prime farmland at the county's edge, with no buildings on it
    3. An undeveloped parcel inside the mapped 100-year floodplain of a river
    4. A former shopping center parking lot in town that is already developed and paved
    Show answer and explanation for question 6

    Correct answer: D · A former shopping center parking lot in town that is already developed and paved

    In LEED v5 BD+C, Sensitive Land Protection can be earned by placing the development footprint on previously developed land, which the old parking lot is. On previously undeveloped land, the footprint must avoid sensitive land as the credit defines it, including prime farmland, floodplains, notable habitat, areas within 100 feet of a water body, areas within 50 feet of a wetland, and protected steep slopes. A footprint 40 feet from a wetland falls inside that 50-foot buffer. Prime farmland and a mapped 100-year floodplain are both on the sensitive list. The paved lot has already lost its natural cover, so building there spares land that still provides ecosystem services.

    Look for this next time: Previously developed sites protect sensitive land; undeveloped sites must avoid farmland, floodplains, habitat, and buffers around water and wetlands.

  7. Question 7 · Location and Transportation

    A company building a new headquarters wants to cut employees' vehicle miles traveled, in line with the LEED v5 BD+C Transportation Demand Management credit. Which plan best supports that goal?

    1. Add parking beyond the standard ratio so that drivers stop circling the block
    2. Provide less parking than the standard ratios and charge a market-rate fee
    3. Give every employee a free reserved space close to the main entrance
    4. Repave the surface lot with lighter-colored concrete to keep it cooler
    Show answer and explanation for question 7

    Correct answer: B · Provide less parking than the standard ratios and charge a market-rate fee

    USGBC's Transportation Demand Management credit for LEED v5 aims to reduce vehicle distance traveled and the related emissions. Its options include reducing parking capacity below the base ratios in the Institute of Transportation Engineers Parking Generation Manual and charging a parking fee at or above the local market rate, alongside bicycle networks, storage, showers, and repair stations. Less parking and a real price make other ways of commuting more attractive. Adding spaces or handing out free reserved ones works against the credit's intent, because ample free parking makes driving the easy choice. Lighter paving belongs to heat island reduction in Sustainable Sites and does not change how people travel.

    Look for this next time: Transportation demand management cuts vehicle miles traveled by limiting and pricing parking and by supporting active travel.

  8. Question 8 · Sustainable Sites

    A LEED v5 BD+C project with a low-sloped roof and a large surface parking lot wants to reduce its heat island effect. Which combination fits the Heat Island Reduction credit?

    1. A dark membrane roof with thicker insulation and new black asphalt paving
    2. A darker roof coating with a lower SRI to cut glare toward neighbors
    3. A vegetated roof with native plants plus tree shade over the parking areas
    4. More open parking spaces paved in standard asphalt with no shading
    Show answer and explanation for question 8

    Correct answer: C · A vegetated roof with native plants plus tree shade over the parking areas

    USGBC's Heat Island Reduction credit for LEED v5 counts nonroof measures such as tree shade over paving, high-reflectance paving, and open-grid pavement, plus roofing that meets minimum solar reflectance index (SRI) values or a vegetated roof using native or adapted plants; covering all parking is another option. EPA notes that green roofs provide shade and lower the temperature of the roof surface and the surrounding air. Extra insulation saves energy inside, but a dark membrane and black asphalt still absorb the sun's heat. EPA explains that a high solar reflectance is what keeps a cool roof cooler, so a lower-SRI coating moves the wrong way. More unshaded asphalt enlarges the hot surface.

    Look for this next time: Shade, vegetation, high-reflectance surfaces, and covered parking reduce heat islands; dark, exposed roofs and paving add to them.

  9. Question 9 · Sustainable Sites

    A LEED v5 BD+C project team wants its site to handle rainwater the way the Rainwater Management credit intends. Which approach fits best?

    1. Keep runoff on the site with rain gardens, permeable paving, and water reuse
    2. Pipe all roof and paving runoff straight into the municipal storm sewer system
    3. Replace planted areas with paving so the site drains to one large outfall
    4. Send all runoff to the nearby creek through one sediment trap
    Show answer and explanation for question 9

    Correct answer: A · Keep runoff on the site with rain gardens, permeable paving, and water reuse

    USGBC's Rainwater Management credit for LEED v5 BD+C aims to reduce runoff volume and improve water quality by replicating the site's natural hydrology. Teams retain the runoff from a chosen percentile of local rainfall events on site, infiltrating, evapotranspiring, or collecting and reusing it through low-impact development and green infrastructure, and reuse for irrigation or flushing can earn an extra point. Piping everything to the storm sewer moves the problem downstream, which the credit's intent wants to avoid. Adding paving increases runoff. A single sediment trap catches some solids but still sends the full volume of runoff to the creek.

    Look for this next time: LEED v5 rainwater management keeps runoff on site through infiltration, evapotranspiration, and reuse instead of sending it downstream.

  10. Question 10 · Water Efficiency

    A corporate campus wants to cut the potable water it uses to irrigate its grounds. Which plan saves the most water?

    1. Keep the existing turf and water it every single morning on a fixed clock schedule
    2. Plant thirsty exotic species and run the sprinklers twice a day in summer
    3. Install new sprinkler heads but keep the old clock timer
    4. Switch to native and adapted plants and add a weather-based irrigation controller
    Show answer and explanation for question 10

    Correct answer: D · Switch to native and adapted plants and add a weather-based irrigation controller

    GBCI's exam specifications list native and adaptive species and smart irrigation controllers under outdoor water use. Species adapted to the local climate are chosen so the landscape needs less irrigation, and EPA's WaterSense program explains that weather-based controllers use local weather and landscape conditions to tailor watering schedules, so watering better matches what plants need, unlike a clock-based controller. Watering turf every morning on a timer ignores rain and season. Thirsty exotic species watered twice a day raise demand. New sprinkler heads may spread water more evenly, but a fixed clock schedule still waters whether the landscape needs it or not.

    Look for this next time: Outdoor water savings come from plants suited to the climate and controllers that water by weather or soil moisture, not by the clock.

  11. Question 11 · Water Efficiency

    A LEED v5 BD+C project buys municipal water and also collects rainwater to flush its toilets. What does the Water Metering and Reporting prerequisite require?

    1. Meter only the municipal supply, because harvested rainwater is exempt
    2. Install one combined meter that records both water sources as a single total
    3. Meter the rainwater separately and share whole-project water use with USGBC
    4. Submit one month of meter readings at certification and nothing after
    Show answer and explanation for question 11

    Correct answer: C · Meter the rainwater separately and share whole-project water use with USGBC

    USGBC's Water Metering and Reporting prerequisite for LEED v5 BD+C requires permanent meters that record total water use from potable and alternative sources, with alternative sources metered separately from municipally supplied potable water. The facility manager or tenants must be able to see the data, and the project commits to sharing whole-project water use with USGBC at least once a year for five years or until the building changes ownership or lessee. Rainwater is an alternative source, so it is not exempt. A single combined meter hides how much each source supplies. One month of readings at certification falls far short of the ongoing reporting commitment.

    Look for this next time: LEED v5 requires permanent water meters, with alternative sources metered separately, and five years of shared whole-project data.

  12. Question 12 · Energy and Atmosphere

    An owner asks why a LEED v5 BD+C project needs a commissioning provider. Which answer describes the purpose of the Fundamental Commissioning prerequisite?

    1. To confirm that the design complies with local building and fire codes
    2. To verify that systems operate according to the owner's project requirements
    3. To benchmark yearly energy use against similar buildings
    4. To certify that the contractor finished all of the work on time and within budget
    Show answer and explanation for question 12

    Correct answer: B · To verify that systems operate according to the owner's project requirements

    USGBC states the intent of Fundamental Commissioning in LEED v5 as improving energy performance and limiting greenhouse gas emissions by verifying that systems operate per the owner's project requirements (OPR). The owner designates a commissioning provider by the end of design development. The provider helps develop the OPR from predesign, reviews the design and contractor submittals against it, and prepares an ongoing commissioning plan for operations. Confirming code compliance is the job of the building official. Benchmarking energy use belongs to energy performance management once the building operates. Schedule and budget are project management measures, not what commissioning verifies.

    Look for this next time: Commissioning verifies that building systems are designed, installed, and operating to meet the owner's project requirements.

  13. Question 13 · Energy and Atmosphere

    An office building buys renewable energy certificates (RECs) equal to its annual electricity use. What does each REC represent?

    1. One metric ton of carbon dioxide emissions avoided or reduced elsewhere
    2. A rebate that lowers the electricity use on the building's meter
    3. A permit to install solar panels on site without a grid connection
    4. The non-power attributes of 1 MWh of electricity from a renewable source
    Show answer and explanation for question 13

    Correct answer: D · The non-power attributes of 1 MWh of electricity from a renewable source

    EPA's Green Power Partnership defines a REC as a market-based instrument that represents the environmental and other non-power attributes of renewable electricity generation, issued when one megawatt-hour is generated and delivered to the grid from a renewable resource. RECs are how buyers substantiate claims to using renewable electricity. One metric ton of emissions avoided or reduced describes a carbon offset, which EPA treats as a different instrument. Buying RECs does not change the electricity a meter records, and RECs have nothing to do with permits for on-site systems. GBCI's exam specifications list RECs with green power under renewable energy practices.

    Look for this next time: A REC carries the environmental attributes of 1 MWh of renewable electricity; a carbon offset represents a metric ton of emissions reduced.

  14. Question 14 · Energy and Atmosphere

    A LEED v5 BD+C design team is choosing a refrigerant for new heat pumps. Its preferred option has zero ozone depletion potential but a global warming potential (GWP) above 700. What does the Fundamental Refrigerant Management prerequisite ask the team to do?

    1. Evaluate lower-GWP alternatives during design and inventory every refrigerant
    2. Nothing extra, because the prerequisite only covers ozone-depleting refrigerants
    3. Switch to a hydrochlorofluorocarbon refrigerant, which the prerequisite favors
    4. Remove all refrigerants, since LEED v5 bans them
    Show answer and explanation for question 14

    Correct answer: A · Evaluate lower-GWP alternatives during design and inventory every refrigerant

    USGBC's Fundamental Refrigerant Management prerequisite for LEED v5 aims to cut greenhouse gas emissions from refrigerants by accelerating the phaseout of high-GWP refrigerants and reducing leaks. Projects that use refrigerants inventory each refrigerant's type, GWP, and amount, use no hydrochlorofluorocarbons in new equipment, evaluate available alternatives during design for any refrigerant with a GWP above 700, and check and repair leaks before substantial completion. Zero ozone depletion does not settle the question, because the prerequisite's focus is global warming potential. Hydrochlorofluorocarbons are barred in new equipment. Using no refrigerants is one way to comply, not a requirement.

    Look for this next time: LEED v5's refrigerant prerequisite targets global warming potential and leaks: inventory refrigerants, avoid HCFCs, and evaluate alternatives above GWP 700.

  15. Question 15 · Materials and Resources

    A LEED v5 BD+C: New Construction team must meet the Quantify and Assess Embodied Carbon prerequisite. Which task fits it?

    1. Projecting the building's annual operational energy use and the emissions it causes
    2. Calculating the cradle-to-gate emissions of the structure, enclosure, and hardscape
    3. Buying carbon offsets equal to the emissions of the construction phase
    4. Tracking how much construction waste avoids the landfill
    Show answer and explanation for question 15

    Correct answer: B · Calculating the cradle-to-gate emissions of the structure, enclosure, and hardscape

    USGBC's prerequisite asks teams to quantify the global warming potential of the project's structure, enclosure, and hardscape materials, using cradle-to-gate (A1–A3) emissions for each material, and to name the top three sources of embodied carbon with the strategies considered to reduce them. EPA describes embodied carbon as the greenhouse gas emissions from extracting, transporting, and manufacturing a product. Operational energy and its emissions fall under the Energy and Atmosphere prerequisite on operational carbon projection. Buying offsets is not part of this prerequisite. Construction and demolition waste diversion is a separate Materials and Resources credit.

    Look for this next time: LEED v5 has BD+C projects measure the cradle-to-gate embodied carbon of their main materials and name the biggest sources.

  16. Question 16 · Materials and Resources

    A specifier wants to compare the greenhouse gas emissions from producing two concrete mixes, using standardized, third-party verified data published by each manufacturer. Which document provides that?

    1. A safety data sheet that lists each mix's hazards and handling precautions
    2. A product warranty that states each mix's expected strength and service life
    3. An environmental product declaration based on a life-cycle assessment
    4. A sales brochure calling each mix eco-friendly
    Show answer and explanation for question 16

    Correct answer: C · An environmental product declaration based on a life-cycle assessment

    EPA's EPD Basics guide describes an environmental product declaration as a document that discloses a product's environmental impacts, such as the greenhouse gas emissions from its production, so products that serve the same function can be compared in a standardized way. An EPD is built on a life-cycle assessment and must receive third-party verification. A safety data sheet covers chemical hazards and safe handling, not life-cycle emissions. A warranty describes performance and service life. A brochure's claims are neither standardized nor independently verified. GBCI's exam specifications list product purchasing and declarations within Materials and Resources.

    Look for this next time: An EPD reports a product's life-cycle environmental impacts, verified by a third party, so similar products can be compared.

  17. Question 17 · Materials and Resources

    A renovation team is deciding what to do with interior doors and solid-wood casework that are still in good condition. Which option does EPA's waste management hierarchy rank as most environmentally preferred?

    1. Shred them for recycling into new composite wood products
    2. Burn them at a waste-to-energy plant to recover electricity
    3. Landfill them, since older materials can't meet current specs
    4. Keep and reuse them in place in the renovated interior
    Show answer and explanation for question 17

    Correct answer: D · Keep and reuse them in place in the renovated interior

    EPA's waste management hierarchy ranks source reduction and reuse as the most environmentally preferred strategy, followed by recycling and composting, then energy recovery, and last treatment and disposal. Reusing the doors and casework in place avoids the impacts of making, shipping, and installing replacements, and LEED v5 BD+C includes a Building and Materials Reuse credit for this kind of decision. Recycling still keeps the wood out of a landfill but uses energy to reprocess it. Energy recovery burns the material and ranks below recycling. Landfilling ranks last, and nothing in the scenario says the items fail current requirements.

    Look for this next time: Reuse ranks above recycling, energy recovery, and disposal, and it avoids the embodied impacts of new materials.

  18. Question 18 · Indoor Environmental Quality

    Midway through construction of a LEED v5 BD+C project, the contractor wants to run the permanent air handlers to dry freshly finished drywall. What does the Construction Management prerequisite call for?

    1. Avoid it, or keep proper filtration and replace all filters before occupancy
    2. Run them without filters to speed up drying
    3. Run them freely once the building is fully enclosed, with no other steps needed
    4. Run them only overnight, when no workers are inside to breathe the dust
    Show answer and explanation for question 18

    Correct answer: A · Avoid it, or keep proper filtration and replace all filters before occupancy

    USGBC's Construction Management prerequisite for LEED v5 asks teams to keep contaminants out of the HVAC system. Permanently installed equipment should not run during construction if possible; if it must, the team maintains proper filtration, replaces all filtration media after construction and before occupancy, and completes testing and balancing with the new filters. Running without filters pulls construction dust into ducts and coils, where it can circulate after move-in. Enclosing the building does not remove the dust that construction creates. Running only at night changes who breathes the air today but still loads the system with contaminants.

    Look for this next time: During construction, protect the HVAC system: avoid running it, or filter properly and replace all filters before occupancy.

  19. Question 19 · Indoor Environmental Quality

    A school district asks why its renovation should specify low-emitting paints, adhesives, and flooring. Which reason is best supported?

    1. They always cost less than conventional products of the same type
    2. They lower the building's energy use by reflecting more daylight
    3. They cut emissions of VOCs, which often run higher indoors than out
    4. They remove the need for ventilation once the building is occupied
    Show answer and explanation for question 19

    Correct answer: C · They cut emissions of VOCs, which often run higher indoors than out

    EPA explains that volatile organic compounds are emitted as gases from certain solids and liquids, including paints and many building products; some have short- and long-term health effects, and concentrations of many VOCs are consistently higher indoors, up to ten times higher, than outdoors. Low-emitting materials reduce those emissions at the source. GBCI's exam specifications list low-emitting materials under indoor air quality, while LEED v5 BD+C places its Low-Emitting Materials credit in Materials and Resources. Price depends on the product. Paint emissions have nothing to do with daylight. Low-emitting products reduce one source of pollutants; they do not make ventilation unnecessary.

    Look for this next time: Low-emitting materials reduce VOC exposure indoors, where many VOC concentrations run higher than outdoors.

  20. Question 20 · Indoor Environmental Quality

    A LEED v5 BD+C office design already meets every locally applicable accessibility code. What more does the Accessibility and Inclusion credit require?

    1. Nothing more, since meeting the local code earns the point
    2. At least 10 listed strategies that go beyond the local accessibility code
    3. An occupant survey on accessibility within one year of move-in
    4. Accessible parking spaces at double the number the local code requires
    Show answer and explanation for question 20

    Correct answer: B · At least 10 listed strategies that go beyond the local accessibility code

    USGBC's Accessibility and Inclusion credit for LEED v5 BD+C aims to support the diverse needs of occupants and a sense of belonging. Projects must meet all locally applicable accessibility codes and also include at least 10 listed strategies that go beyond those codes, grouped under physical diversity, safety and aging, social health, and navigation. Examples include nonslip flooring, audible and visual emergency alerts, an all-gender restroom on each floor, and tactile maps for wayfinding. Code compliance is the starting point, not the credit. A post-occupancy survey and extra accessible parking are not among the credit's listed requirements.

    Look for this next time: LEED v5's Accessibility and Inclusion credit starts at code compliance and adds at least 10 strategies beyond it.

Use the sample well

The rationale matters more than the score.

A short set can show you what deserves another look. A strong run shows you can apply LEED v5 to project decisions: picking the right rating system, telling a prerequisite from a credit, and choosing strategies that cut carbon, water use, and indoor pollutants. Twenty questions are a small sample, so the result does not predict a 170 on GBCI's 125–200 scale.

01

Answer before reviewing

Choose the one best answer for the project as described. Then read why each other option falls short.