20 free CAPM practice questions

Twenty original CAPM questions across the four domains of PMI's 2023 CAPM exam content outline, from projects versus operations and critical path math to Scrum, Kanban, and business analysis tools. The items follow the domain weights (7, 3, 4, and 6 items), but 20 items cannot match the real exam's topic mix or difficulty, and your score here does not predict a pass.

Start question 1

These are original Passy questions written for CAPM exam preparation. They are not official PMI items, not taken from PMI's CAPM exam prep course or practice materials, and not recalled exam questions. Each is a single-answer item with four options; this web set does not include the drag-and-drop, hot spot, animation, or comic strip items the real exam can use. The items are split across the four domains approximately in proportion to their weights in the CAPM Examination Content Outline (2023 Exam Update): 7, 3, 4, and 6 items, in outline order. Twenty items cannot match the real exam's mix or difficulty, and your results here do not predict a pass.

Quick PracticeQuestion 1 of 20
Your progress through this set
Project Management Fundamentals and Core ConceptsStep 1 · Choose one answer

A regional bank's payroll team runs payroll every two weeks, following the same steps each cycle. The bank has also approved a nine-month initiative to replace its payroll software, with a fixed budget and a go-live date. Which statement correctly classifies this work?

Question review

All 20 CAPM questions with explanations

Try the set above first, then use this list to review. Each answer and explanation stays closed until you open it.

  1. Question 1 · Project Management Fundamentals and Core Concepts

    A regional bank's payroll team runs payroll every two weeks, following the same steps each cycle. The bank has also approved a nine-month initiative to replace its payroll software, with a fixed budget and a go-live date. Which statement correctly classifies this work?

    1. Both are projects, because each produces a deliverable on a schedule
    2. Both are operations, because both support the payroll function
    3. The payroll runs are operations; the software replacement is a project
    4. The payroll runs are a program, and the replacement is one of its projects
    Show answer and explanation for question 1

    Correct answer: C · The payroll runs are operations; the software replacement is a project

    PMI describes a project as temporary work, with a beginning and an end, undertaken to create a unique result, while operations are ongoing, repetitive work that sustains the business. The biweekly payroll runs repeat the same process with no planned end, so they are operations. The software replacement has a start, a fixed go-live date, a budget, and a unique result, so it is a project; when it ends, its output passes to the payroll operation. Producing output on a schedule does not turn repetitive work into a project, and supporting the same function does not make a temporary initiative operational. A program is a group of related projects managed together for shared benefits, not a label for routine work.

    Look for this next time: Projects are temporary and create a unique result; operations repeat the same work to sustain the business.

  2. Question 2 · Project Management Fundamentals and Core Concepts

    While planning an office move, the project manager records four items: the landlord might not finish the new space on time; the move must cost no more than $80,000; the team expects the movers to be available on the planned weekend; and the network vendor has already missed its first installation date. Which item is a constraint?

    1. The landlord might not finish the new space on time
    2. The move must cost no more than $80,000
    3. The team expects the movers to be available that weekend
    4. The network vendor has already missed its first installation date
    Show answer and explanation for question 2

    Correct answer: B · The move must cost no more than $80,000

    A constraint is a limiting factor the project must work within, such as a budget ceiling, a mandated date, or a required standard. The $80,000 cap limits the options the team can choose, so it is a constraint. The landlord's possible delay is a risk: an uncertain event that has not happened and may or may not occur. The expectation that the movers will be available is an assumption: something treated as true for planning without proof, which should be logged and checked. The vendor's missed date is an issue, because it has already happened and now has to be managed. The CAPM outline lists telling these four apart as part of its first task.

    Look for this next time: Constraints limit options, risks may happen, assumptions are unproven planning beliefs, and issues have already happened.

  3. Question 3 · Project Management Fundamentals and Core Concepts

    A hospital group is running three related projects: a new patient portal, a scheduling system upgrade, and staff training on both. They depend on one another, and leaders coordinate them to deliver one benefit, faster patient access. Separately, the executive committee selects and funds all of the group's projects, programs, and operations. What is the coordinated set of three projects?

    1. A program, because related projects are coordinated for shared benefits
    2. A portfolio, because it contains more than one project
    3. A phase, because the work is divided into sequential stages
    4. An operation, because the hospital will use the systems every day
    Show answer and explanation for question 3

    Correct answer: A · A program, because related projects are coordinated for shared benefits

    PMI's program standard describes a program as related projects, subsidiary programs, and program activities managed in a coordinated way to obtain benefits not available from managing them individually. The portal, the scheduling upgrade, and the training depend on one another and share one benefit, so together they form a program. A portfolio is a collection of projects, programs, and operations managed as a group to achieve strategic objectives; the executive committee's selection and funding of all the group's work is the portfolio level, and portfolio components need not be related. A phase is part of a single project's life cycle, not a group of projects. Daily use of the systems after delivery is operations.

    Look for this next time: A program coordinates related projects for shared benefits; a portfolio groups work, related or not, to meet strategic objectives.

  4. Question 4 · Project Management Fundamentals and Core Concepts

    A project manager is evaluating three vendor bids for a software contract and will recommend the winner to the sponsor. One bidder is a firm co-owned by the project manager's sister. The bids are close, and the project manager believes they can judge them fairly. Under PMI's Code of Ethics and Professional Conduct, what should the project manager do?

    1. Evaluate the bids as planned, since the project manager can still judge them fairly
    2. Recommend another vendor so no one can claim the sister's firm was favored
    3. Ask the sister's firm to withdraw its bid before the evaluation starts
    4. Disclose the relationship and step back unless stakeholders approve a plan
    Show answer and explanation for question 4

    Correct answer: D · Disclose the relationship and step back unless stakeholders approve a plan

    PMI's Code of Ethics and Professional Conduct makes disclosing real or potential conflicts of interest a mandatory fairness standard. It also says to treat even the appearance of a conflict as a conflict, and to refrain from influencing the decision unless the conflict has been fully disclosed to the appropriate stakeholders, a mitigation plan has been approved, and those stakeholders consent to proceed. Evaluating the bids anyway relies on the project manager's own sense of fairness, which the Code says is not enough. Recommending a different vendor to avoid criticism is still a decision shaped by the relationship, and it is unfair to the sister's firm. Asking a bidder to withdraw goes beyond the project manager's role and skips disclosure.

    Look for this next time: Disclose any real or potential conflict of interest, and step back from the decision unless stakeholders approve a way forward.

  5. Question 5 · Project Management Fundamentals and Core Concepts

    A new project manager and a sponsor are agreeing how they will divide responsibilities on a warehouse automation project. Which responsibility usually belongs to the sponsor rather than to the project manager?

    1. Leading the project team and coordinating the day-to-day work
    2. Maintaining the schedule and tracking progress against it
    3. Providing resources and championing the business case with senior leaders
    4. Running team meetings and resolving everyday conflicts within the team
    Show answer and explanation for question 5

    Correct answer: C · Providing resources and championing the business case with senior leaders

    PMI describes the sponsor as the person or group that provides resources and support for the project and is accountable for enabling its success. Sponsors typically champion the business case, secure and release funding, help remove obstacles beyond the project manager's authority, and make decisions that exceed it. The project manager is the person the organization assigns to lead the team that achieves the project objectives, so leading and coordinating daily work, maintaining the schedule, and running team meetings and handling routine conflicts are project manager responsibilities. Mixing up the two roles leads either to escalating routine decisions to the sponsor or to a project manager trying to make funding decisions that belong to the sponsor.

    Look for this next time: Sponsors provide resources and champion the business case; project managers lead the team and manage the daily work.

  6. Question 6 · Project Management Fundamentals and Core Concepts

    A project manager is building a schedule for a product launch. It includes "Regulatory approval received" and "Prepare launch materials (10 days)." A team member asks why the schedule shows a duration for one item but not the other. What is the best explanation?

    1. Approval received is a milestone, a point in time with zero duration
    2. Both are activities, but the approval's duration is unknown, so it is blank
    3. Both are milestones, and only critical-path milestones get a duration
    4. Approval is a work package, and work packages never carry durations
    Show answer and explanation for question 6

    Correct answer: A · Approval received is a milestone, a point in time with zero duration

    A milestone is a significant point or event in a project, so it marks a moment, such as an approval being received, and has zero duration. Preparing launch materials is an activity: work that consumes time and resources, so it carries an estimated duration of 10 days. Leaving a duration blank because it is unknown would hide a schedule risk; unknown durations are estimated, not omitted. Milestones have no duration whether or not they sit on the critical path. A work package is the lowest level of the work breakdown structure, and it is decomposed into activities, which do have durations. The CAPM outline asks candidates to distinguish a milestone from a task duration.

    Look for this next time: Milestones mark significant points in time and have zero duration; activities consume time and carry estimated durations.

  7. Question 7 · Project Management Fundamentals and Core Concepts

    A project's weekly status meeting has no agenda, often runs 30 minutes over, and ends without clear decisions. Several team members have stopped attending. Which change would most improve the meeting's effectiveness?

    1. Make attendance mandatory and record who is absent each week
    2. Send an agenda with objectives and time limits, then record decisions and owners
    3. Double the scheduled length so there is time to cover every topic
    4. Replace the weekly meeting with longer status emails written by each team member
    Show answer and explanation for question 7

    Correct answer: B · Send an agenda with objectives and time limits, then record decisions and owners

    An effective meeting has a clear purpose, an agenda shared in advance, time limits, the right attendees, and recorded outcomes: decisions and action items with owners and due dates. Those elements address both problems here, the overruns and the missing decisions. Making attendance mandatory treats the symptom; people stopped coming because the meeting wastes their time. Doubling the length rewards the lack of structure and takes more of everyone's time. Status emails can replace some updates, but they do not produce the decisions the meeting is failing to reach. The CAPM outline lists evaluating the effectiveness of a meeting under its task on problem-solving tools and techniques.

    Look for this next time: Meetings work when they have a clear purpose, a shared agenda, time limits, and recorded decisions with owners.

  8. Question 8 · Predictive, Plan-Based Methodologies

    A small predictive project has four activities. A (3 days) starts the project. B (5 days) and C (2 days) both start after A finishes. D (4 days) starts after both B and C finish. What are the project's duration and the total float of activity C?

    1. 9 days, and C has no float because it is on the critical path
    2. 12 days, and C has 3 days of total float
    3. 14 days, and C has 5 days of total float
    4. 12 days, and C has 5 days of total float
    Show answer and explanation for question 8

    Correct answer: B · 12 days, and C has 3 days of total float

    List the paths through the network and add their durations. A-B-D takes 3 + 5 + 4 = 12 days, and A-C-D takes 3 + 2 + 4 = 9 days. The longest path, A-B-D, is the critical path, so the project takes 12 days. C sits on the shorter path, and its total float is the difference between the two paths: 12 − 9 = 3 days, so C can slip up to 3 days without delaying the finish. A 9-day answer uses the shortest path and leaves B's extra work out. Adding all four durations (3 + 5 + 2 + 4 = 14) ignores the fact that B and C run in parallel. Five days of float overstates C's slack: C's 2 days plus 3 days of float equal B's 5 days.

    Look for this next time: The critical path is the longest path; float on another path is the gap between its length and the critical path's.

  9. Question 9 · Predictive, Plan-Based Methodologies

    At the end of month 4, a predictive project shows planned value (PV) of $60,000, earned value (EV) of $54,000, and actual cost (AC) of $50,000. What are the cost variance (CV) and schedule variance (SV), and what do they indicate?

    1. CV = +$4,000 and SV = −$6,000: under budget and behind schedule
    2. CV = −$4,000 and SV = +$6,000: over budget and ahead of schedule
    3. CV = +$10,000 and SV = −$6,000: under budget and behind schedule
    4. CV = −$6,000 and SV = +$4,000: over budget and ahead of schedule
    Show answer and explanation for question 9

    Correct answer: A · CV = +$4,000 and SV = −$6,000: under budget and behind schedule

    Cost variance compares the value of the work done with what it cost: CV = EV − AC = $54,000 − $50,000 = +$4,000, so the project is under budget for the work completed. Schedule variance compares the work done with the work planned: SV = EV − PV = $54,000 − $60,000 = −$6,000, so less work is done than planned and the project is behind schedule. Reversing the subtractions flips both signs and both conclusions. A CV of $10,000 comes from PV − AC ($60,000 − $50,000), which compares the plan with spending and ignores how much work is actually done. Pairing −$6,000 with cost and +$4,000 with schedule mixes up the two formulas. Both variances start from earned value.

    Look for this next time: Both variances start from earned value: CV = EV − AC and SV = EV − PV; negative means over budget or behind schedule.

  10. Question 10 · Predictive, Plan-Based Methodologies

    An organization is choosing delivery approaches for four new projects and wants detailed upfront plans only where they will pay off. Which project is best suited to a predictive, plan-based approach?

    1. A mobile app for a new market, where user needs are still unclear
    2. A research prototype whose technical solution has not yet been found
    3. A marketing website whose content will change every week based on visitor data
    4. A warehouse expansion with an approved design, permits, and costly late changes
    Show answer and explanation for question 10

    Correct answer: D · A warehouse expansion with an approved design, permits, and costly late changes

    A predictive, plan-based approach suits work whose scope and requirements can be defined early and are expected to stay stable, and where late changes are expensive, so detailed upfront planning and a baseline pay off. A warehouse expansion with an approved design and permits fits that profile: the deliverable is well understood, construction follows a logical sequence, and rework after the concrete is poured is costly. The mobile app, the research prototype, and the weekly-changing website all carry high uncertainty about requirements or the solution, which favors adaptive approaches that deliver in short cycles and use feedback to adjust. The CAPM outline asks when a predictive, plan-based approach is appropriate.

    Look for this next time: Choose a predictive approach when scope is well defined and stable and late changes are expensive.

  11. Question 11 · Agile Frameworks/Methodologies

    An agile team's velocity over its last four two-week iterations was 16, 25, 19, and 20 story points. The remaining release backlog is estimated at 100 points, and the team's makeup will not change. About how many more iterations should the team forecast to finish the release?

    1. 4 iterations, because the team reached 25 points once
    2. 7 iterations, using the lowest velocity of 16 points
    3. 5 iterations, using the average velocity of 20 points
    4. No forecast is possible, because adaptive teams do not plan releases
    Show answer and explanation for question 11

    Correct answer: C · 5 iterations, using the average velocity of 20 points

    Velocity is the amount of work, here in story points, that a team completes in an iteration, and its recent average is the usual basis for a forecast. The average is (16 + 25 + 19 + 20) ÷ 4 = 80 ÷ 4 = 20 points, so 100 remaining points ÷ 20 = 5 iterations. Forecasting from the single best iteration (100 ÷ 25 = 4) assumes the team's peak will repeat every time, and using the worst (100 ÷ 16 = 6.25, rounded up to 7) assumes the low point will. Adaptive teams do forecast releases; they update the forecast every iteration as velocity and the backlog change, instead of treating it as a fixed commitment.

    Look for this next time: Forecast remaining iterations by dividing the remaining backlog by recent average velocity, and update the forecast every iteration.

  12. Question 12 · Agile Frameworks/Methodologies

    A team uses a Kanban board with To Do, In Progress, Testing, and Done columns. Work is piling up in Testing while developers keep pulling new items into In Progress, and lead times are growing. Which Kanban practice addresses this most directly?

    1. Add a separate column for items that are finished but still waiting to be tested
    2. Give each developer a fixed number of new items to start each week
    3. Switch to two-week sprints with a fixed sprint backlog
    4. Set and enforce work-in-progress limits so items finish before new ones start
    Show answer and explanation for question 12

    Correct answer: D · Set and enforce work-in-progress limits so items finish before new ones start

    Kanban manages flow by visualizing work and limiting work in progress (WIP). The Agile Alliance describes WIP limits as a way to decide when to start new items and to smooth the flow of work. A limit on In Progress and Testing stops developers from pulling new items while work waits for testing, so the team helps clear the bottleneck and finishes what it started, which shortens lead times. A waiting column makes the queue more visible, but on its own it does not stop the queue from growing. Assigning a fixed number of new starts pushes more work into the system regardless of downstream capacity. Switching to sprints changes the method instead of fixing the flow problem.

    Look for this next time: In Kanban, limit work in progress so the team finishes items before starting new ones; that shortens lead time.

  13. Question 13 · Agile Frameworks/Methodologies

    At the end of a sprint, a Scrum team holds two meetings. In the first, stakeholders see the working increment and suggest changes to the product backlog. In the second, the team discusses how it worked together and chooses improvements for the next sprint. Which pairing is correct?

    1. The first is the sprint review; the second is the sprint retrospective
    2. The first is sprint planning; the second is the daily scrum
    3. The first is the sprint retrospective; the second is the sprint review
    4. The first is backlog refinement; the second is sprint planning
    Show answer and explanation for question 13

    Correct answer: A · The first is the sprint review; the second is the sprint retrospective

    In the 2020 Scrum Guide, the sprint review inspects the outcome of the sprint and determines future adaptations: the team presents its work to key stakeholders, and the product backlog may be adjusted. The sprint retrospective is where the team plans ways to increase quality and effectiveness, looking at individuals, interactions, processes, tools, and its Definition of Done. Reversing the two confuses product feedback with process improvement. Sprint planning starts a sprint, and the daily scrum is a short daily check on progress toward the sprint goal. Backlog refinement is an ongoing activity, not an end-of-sprint event. The CAPM outline lists Scrum among the methodologies whose components candidates should distinguish.

    Look for this next time: The sprint review inspects the product with stakeholders; the retrospective improves how the team works.

  14. Question 14 · Agile Frameworks/Methodologies

    A software team writes automated tests before writing the code they check, pairs two developers at one workstation for production code, and integrates and builds its code several times a day. Which agile methodology are these practices most closely associated with?

    1. Kanban
    2. Extreme Programming (XP)
    3. Scaled Agile Framework (SAFe)
    4. Scrum
    Show answer and explanation for question 14

    Correct answer: B · Extreme Programming (XP)

    Test-first programming, pair programming, and continuous integration are core Extreme Programming practices; the Agile Alliance glossary lists all three among XP's practices. XP centers on engineering practices that keep code quality high while requirements change. Scrum is a framework of roles, events, and artifacts and does not prescribe engineering practices, although many Scrum teams adopt XP's. Kanban manages flow through visualization and work-in-progress limits rather than coding practices. SAFe is a framework for coordinating many agile teams across an enterprise; it can include XP practices, but it is defined by its scaling structures. The CAPM outline names Scrum, XP, SAFe, and Kanban as methodologies whose components candidates should distinguish.

    Look for this next time: Pair programming, test-first development, and continuous integration are hallmark Extreme Programming (XP) practices.

  15. Question 15 · Business Analysis Frameworks

    A company is replacing its accounts payable system, and the CFO sponsors and funds the project. The finance director is accountable for how the end-to-end invoice approval process performs and sets its rules. The agile team building the new workflow has a product owner who orders the backlog. Which role does the finance director hold for this work?

    1. Product owner, because the director cares about the outcome
    2. Project sponsor, because the director is a senior manager
    3. Process owner, accountable for the approval process and its rules
    4. Business analyst, because the director will define requirements
    Show answer and explanation for question 15

    Correct answer: C · Process owner, accountable for the approval process and its rules

    A process owner is accountable for the design and performance of a business process, including its rules and how well it meets its goals, across the teams that run it. That describes the finance director's relationship to invoice approval. The product owner on an agile team is accountable for maximizing the product's value and ordering the backlog, a role that is already filled. The CFO funds and champions the project, so the sponsor role is taken, and seniority alone does not make someone a sponsor. A business analyst elicits, analyzes, and manages requirements; the director will supply requirements as a stakeholder, not perform that role. The CAPM outline asks candidates to distinguish stakeholder roles such as process owner and product owner.

    Look for this next time: A process owner is accountable for a business process's design, rules, and performance; a product owner maximizes product value through the backlog.

  16. Question 16 · Business Analysis Frameworks

    A business analyst learns that a regulatory change will alter requirements already agreed with three teams: finance, operations, and IT. The teams' priorities conflict, and they must agree on a new approach before development continues next week. Which communication approach should the analyst choose?

    1. Email a summary of the change to all three teams and ask for replies by Friday
    2. Hold a facilitated session with the three teams to review the impact and agree
    3. Post the updated requirements on the wiki and let each team adapt its plans
    4. Brief each team lead separately, then decide based on what each one says
    Show answer and explanation for question 16

    Correct answer: B · Hold a facilitated session with the three teams to review the impact and agree

    The channel should fit the message and its purpose. This message is complex, affects several groups whose priorities conflict, and needs a joint decision within a week, so an interactive, facilitated session, in person or by video, lets the teams see the impact together, surface their conflicts, and agree on an approach. An email or a wiki post is one-way communication: fine for informing people, but poor at resolving disagreement and slow at reaching a decision. Separate briefings can help prepare people, but deciding from three separate conversations leaves the conflicts between teams unresolved and gives no one shared ownership of the decision. The CAPM outline asks candidates to recommend the most appropriate communication channel or tool.

    Look for this next time: Use interactive, facilitated communication when a message is complex, affects groups that disagree, and needs a joint decision.

  17. Question 17 · Business Analysis Frameworks

    A business analyst needs input from about 3,000 customers in 12 countries on which of eight proposed self-service features they would use. Results must be collected within two weeks and compared across regions. Which elicitation technique fits best?

    1. One-on-one interviews with a broad sample of customers in each country
    2. A requirements workshop with customer representatives from every country
    3. Observing customers as they use the current self-service tools
    4. A structured online survey with the same closed questions for everyone
    Show answer and explanation for question 17

    Correct answer: D · A structured online survey with the same closed questions for everyone

    Surveys, or questionnaires, gather information from many respondents quickly and at low cost, even when they are spread across locations, and closed questions produce answers that can be counted and compared across regions. That fits 3,000 customers, 12 countries, eight features, and a two-week window. Interviews give depth but are slow and costly at this scale. A workshop brings a small group together to explore and agree on requirements; it cannot reliably represent thousands of customers, and convening people from 12 countries in two weeks is hard. Observation shows how people use today's tools, but not which proposed features they want. The CAPM outline asks candidates to identify the requirements-gathering approach that fits a situation.

    Look for this next time: Use surveys for comparable input from many dispersed stakeholders quickly; use interviews or workshops when you need depth.

  18. Question 18 · Business Analysis Frameworks

    Executives at a software company want a single view of which major capabilities of a new product are planned for each of the next four quarterly releases, so marketing and sales can align their plans. Which artifact should the business analyst help create?

    1. A product roadmap showing themes and features across the planned releases
    2. A detailed task schedule listing every development activity and its owner
    3. A requirements traceability matrix linking requirements to test cases
    4. A sprint backlog listing the items the team committed to this iteration
    Show answer and explanation for question 18

    Correct answer: A · A product roadmap showing themes and features across the planned releases

    A product roadmap is a high-level, time-based view of where a product is going: the themes, capabilities, or features planned for upcoming releases. It communicates direction to executives and to teams such as marketing and sales without the detail of individual tasks, and it is updated as priorities change. A detailed task schedule is too granular for this audience and this question. A requirements traceability matrix tracks each requirement from its source through delivery and testing; it does not show what is planned for each release. A sprint backlog covers only the current iteration. The CAPM outline asks candidates to explain how a product roadmap is used and which components go into which releases.

    Look for this next time: A product roadmap gives a high-level, time-based view of which capabilities are planned for which releases.

  19. Question 19 · Business Analysis Frameworks

    A business analyst moves from a predictive project, where all requirements were documented and signed off before design began, to an agile team. How will the analyst's requirements work most likely change?

    1. Requirements are no longer documented, so the analyst's role ends at kickoff
    2. The analyst signs off a complete requirements specification before the first iteration
    3. The analyst refines backlog items with the product owner just in time, each iteration
    4. The analyst hands all requirements work to the developers to write their own stories
    Show answer and explanation for question 19

    Correct answer: C · The analyst refines backlog items with the product owner just in time, each iteration

    In adaptive approaches, requirements are elaborated progressively. The business analyst, often working with or supporting the product owner, refines backlog items into stories with acceptance criteria shortly before the team needs them, and revisits them as feedback arrives each iteration. In predictive approaches, much of the analysis happens upfront and the requirements are baselined. Agile teams still document requirements, in a lighter and evolving form, so the analyst's role does not end. Signing off a complete specification before the first iteration reverts to a predictive approach. Developers do help refine stories, but handing them all the requirements work drops the analysis and stakeholder collaboration the analyst provides. The CAPM outline asks how methodologies shape the analyst's role.

    Look for this next time: In agile work, the business analyst refines requirements progressively with the product owner instead of finalizing them all upfront.

  20. Question 20 · Business Analysis Frameworks

    Before a release, a business analyst must confirm that every approved requirement has been built and has passed its tests, and that no feature was added without a requirement behind it. Which tool supports this check most directly?

    1. The stakeholder register and engagement plan
    2. The risk register and risk report
    3. The project charter and business case
    4. The requirements traceability matrix
    Show answer and explanation for question 20

    Correct answer: D · The requirements traceability matrix

    A requirements traceability matrix links each requirement back to its origin, such as a business objective, and forward to the deliverables and test cases that satisfy it. Reading forward shows whether every approved requirement has been built and tested; reading backward shows whether any delivered feature lacks a requirement, a sign of scope creep. The stakeholder register records who the stakeholders are and what they care about, the risk register tracks uncertain events and their responses, and the charter authorizes the project at a high level. None of them traces requirements through to testing. The CAPM outline names the requirements traceability matrix or the product backlog as the basis for judging readiness for delivery.

    Look for this next time: Use a requirements traceability matrix to confirm each requirement is built and tested, and that nothing was added without one.

Use the sample well

The rationale matters more than the score.

A short set can show you what deserves another look. Twenty questions are a small sample, so this set cannot measure readiness for the 150-question CAPM exam or predict a pass.

01

Answer before reviewing

Decide whether the situation is predictive, agile, or about business analysis, pick the one best answer, and read why each other option falls short.

02

Read every rationale

Confirm why the best option fits, even when you were right.

03

Follow the pattern

Use recurring misses—not one score—to choose your next focus.