Journeyman Plumber Exam guideStudy & preparation

Washington Plumber Exam: Rehearse the Two Sizing Exercises

Published 6 min read2 official sources

Short answer

Rehearse Washington's two sizing exercises by recording fixture units and minimum pipe sizes for each labeled segment, first while learning the rules and then with only the supplied tables available. Washington L&I describes a closed-book exam with 100 code questions, a waste-and-vent sizing exercise and a water-piping sizing exercise. Its instructions, checked November 11, 2026, supply Tables 702.1, 610.3, 610.4 and 610.10, but not Table 703.2. Use the exam's specified code edition and Washington amendments to check your work afterward.

What are the three parts of Washington's exam?

Practice Washington's sizing exercises by tracing each labeled pipe segment, recording its fixture units and selecting its minimum permitted size under the exam's code. The Washington Department of Labor and Industries (L&I) describes a closed-book exam with 100 code questions plus separate waste-and-vent and water-piping sizing exercises; these instructions were checked November 11, 2026.

PartWhat L&I describesWhat to practice
Code questions100 questions from chapters 1–10, 15, 16 and 17Recall the applicable rules without opening the book
Waste and vent sizingA drawing-based exercise using chapter 7Identify the fixture units and minimum waste and vent sizes requested
Water piping sizingA drawing-based exercise using chapter 6Identify the fixture units and minimum hot and cold water sizes requested

The rehearsal method below is an editorial study suggestion, not an L&I scoring procedure or a reproduction of its drawings. Keep three separate records: code questions you miss, waste-and-vent segments you cannot size, and water-piping segments you cannot size. A strong result on one record does not fill an unanswered row in another. For the code-question record, original questions on the code concepts these exams share are planned for full journeyman plumber prep, without Washington's amendments.

For the broader comparison with other exam providers, use the journeyman plumber exam format guide. Here, the next step is to set up a practice desk that matches Washington's reference restriction.

Which tables are supplied and which must you prepare without?

L&I's instructions, checked November 11, 2026, name the 2015 Uniform Plumbing Code (UPC) with Washington amendments as the exam basis. They list Tables 702.1, 610.3, 610.4 and 610.10 as supplied. Table 703.2 is not supplied. That last distinction should change how you rehearse.

Use two passes through a practice drawing:

  1. Learning pass: use the specified code and amendments to understand each step. Record the governing section, table, column and relevant note beside the answer. Include any step that depends on Table 703.2.
  2. Restricted-reference pass: close the code and put away your answer key and notes. Keep only the four listed tables available as references. Work a fresh copy of the drawing and leave an honest marker beside anything you cannot finish.

If a step stalls because you need Table 703.2 or another unsupplied rule, record that dependency. Study it after the pass, then retry without opening that reference. Four supplied tables do not mean every rule needed for the exercise will be available to look up.

Use L&I's Plumber Examination instructions to confirm the reference list before your appointment. The plumbing code edition guide explains why the edition named for an exam needs its own check. Do not substitute a newer book or another state's amended table merely because it is already on your desk.

How do you rehearse the waste-and-vent exercise?

Start with a practice drawing that has a checked solution under the specified code. Before selecting sizes, copy every requested segment label onto a worksheet. This gives you a place to distinguish an incorrect size from a segment you skipped entirely.

For an original inventory drill, imagine a drawing with three fixtures labeled F1, F2 and F3. Segment D-A carries F1 and F2; D-B receives D-A and F3. Before doing any code calculation, the inventory for D-B should name F1, F2 and F3 once each. This is only a tracing exercise: it supplies no fixture-unit values, vent arrangement or compliant pipe sizes.

For a full sizing rehearsal, use the actual fixture descriptions and connections in your practice problem. Then copy this blank log for as many segments as it asks you to size:

Record for each requested waste or vent segmentSegment ___Segment ___
Fixture labels traced to this segment______
Fixture descriptions and applicable conditions______
Fixture-unit entries and total required by the problem______
Governing rule, table, column and note______
Minimum size selected, with units______
Checked answer and reason for any correction______

During the learning pass, show the fixture-unit entries before their total. During the restricted pass, keep those calculations visible but put the checked answer away. For each vent segment, identify the governing vent rule rather than carrying over a waste-pipe answer without checking its applicability.

Review the inventory before changing a size. If you counted F2 twice in the imaginary D-B branch, fix that count first and follow the correction through the affected work. Do not change the fixture inventory, table choice and selected size simultaneously; you would lose the evidence of what caused the error. For drainage concepts outside the drawing, 85 Sanitary Drainage questions are planned for journeyman plumber prep at launch.

How do you rehearse the hot-and-cold water exercise?

Create a new log for the chapter 6 exercise. Label the service for each requested segment before recording its load. Use the connections and conditions shown in the practice drawing, and obtain the applicable fixture-unit values from the exam's code materials during the learning pass.

As a simple inventory-only drill, suppose a fictional drawing explicitly connects H-A to F1 and F2, while C-A connects to F1, F2 and F3. Write those two inventories separately. These labels describe the hypothetical problem; they do not assign hot or cold connections to any real fixture type.

Record for each requested water segmentSegment ___Segment ___
Service identified on drawing: hot or cold______
Connected fixture labels and descriptions______
Applicable water fixture-unit entries and total______
Other conditions required by the sizing method______
Governing rule, table, column and note______
Minimum size selected, with units______
Checked answer and reason for any correction______

Use the “other conditions” row to record what the chosen sizing method requires and where the practice problem supplies it. If a necessary condition is missing, mark the exercise incomplete instead of silently inventing an input. A fixture-unit total is a recorded step, not a completed pipe-size answer.

On the restricted-reference pass, keep Tables 610.3, 610.4 and 610.10 available within the four-table set L&I lists. Select the applicable table and conditions for the problem; the presence of a table does not make every entry in it relevant. Finish by matching each answer to its segment label and service.

How do you review errors without changing several inputs at once?

Check each unfinished or incorrect row in a fixed order: segment identification, fixture inventory, fixture-unit entries, arithmetic, governing rule, minimum size, answer label. Stop at the first mismatch, explain it in one sentence, and then recalculate the affected work.

For example, “I included F3 in H-A even though the practice drawing connects it only to C-A” identifies an inventory error. “I needed an unsupplied reference to choose the size” identifies a recall gap. Those need different follow-up practice, even if both initially produced the same wrong size.

Use the 20 free journeyman plumber practice questions for additional shared plumbing and code practice, and the free study plan to organize study time. These tools follow ICC coverage. The ICC bulletin describes an open-book national exam, so add these Washington drawing rehearsals separately; the tools do not recreate Washington's two exercises or their reference restriction.

For your next session, choose one checked practice drawing, prepare both blank logs and complete a restricted-reference pass. Keep your original answers when correcting them. Repeat the particular step that failed before attempting another whole drawing. Between sessions, short flashcard reviews planned for full journeyman plumber prep can help with terms you need without a book.

Trust the source

Official sources

Exam policies can change. Use these primary sources for the most current details.